Urda crash: Puente expects to reopen the AVE line within 10 days at most after court approval

Transport Minister Óscar Puente estimates that high-speed rail between Madrid and Andalusia can resume within a maximum of ten calendar days once the judge authorizes rebuilding the track in Urda (Toledo), with fewer services and a second human controller whenever the automatic safety systems fail.

Corroborated by independent sources Certainty high

Transport Minister Óscar Puente said on Tuesday that “within a maximum of 10 calendar days” the Madrid-Seville high-speed line can be put back into service once the court authorizes reconstruction work at the site of the Urda (Toledo) collision, according to Europa Press, as reported by Infobae, and El Debate. “Right now we depend on the permission the court gives us,” he said at the press conference after the Council of Ministers. According to those sources, the ministry requested authorization that same Tuesday, after the removal of the wrecked trains was completed.

The damaged track exceeds 40 metres, but as a precaution work will be carried out on a section of about 400 metres, according to Europa Press and El Mira. When it reopens, the line will run with fewer services until the deployment of the ERTMS level 2 control system and an extraordinary review of its safety systems are completed. Europa Press and El Mira attribute that review to the State Railway Safety Agency, while El Debate says it will be carried out by the technical accident investigation authority (AITAT). According to El Mira, Puente gave the example of one train every fifteen minutes instead of every five, six or ten, although with double-unit trains to maintain the number of seats. No specific reopening date has been given.

Puente also announced that, when automatic protection systems such as LZB or ERTMS are not operational, train movement orders will have to be supervised and approved by “at least a second human controller,” according to El Debate and OKDiario.

The collision between a Renfe AVE and an Iryo train occurred on October 28. The official death toll is 69, all of them now identified. The causes remain under judicial and technical investigation, and high-speed rail services between Madrid and Andalusia remain suspended.

This story stands on its own facts. The Post Apocalyptic does not link it to other incidents unless the sources demonstrate a connection.

Sources

  1. Puente prevé abrir con menos frecuencias la línea Madrid-Sevilla en máximo 10 días desde el permiso judicial Infobae (Europa Press) · infobae.com · News agency · Confirms · accessed 3 Nov 2026, 14:22 CET
  2. Puente anuncia un segundo controlador para evitar fallos como el de Urda y reducirá los trenes en la línea Madrid-Sevilla El Debate · eldebate.com · News outlet · Confirms · accessed 3 Nov 2026, 14:22 CET
  3. 40 metros de vía y 10 días de obra: el plan de Óscar Puente para reabrir la alta velocidad Madrid-Sevilla tras Urda El Mira · elmira.es · News outlet · Confirms · accessed 3 Nov 2026, 14:22 CET
  4. Accidente de tren en Toledo, en directo: última hora de las víctimas, las ayudas y la investigación del accidente de Urda OKDiario · okdiario.com · News outlet · Confirms · accessed 3 Nov 2026, 14:22 CET

Public history

  • — Published (selected and written by an AI assistant under our published editorial standards)